From 14 December 2027, the EU Forced Labour Regulation bars products made with forced labour from the EU market, and it does not give importers a certificate to collect. What it gives authorities is the power to investigate a product and ask the companies involved for information. The Commission’s guidelines, published on 3 September 2026, list the kinds of information an authority may ask for. An importer of flooring can ask a factory for the same kinds of information now, long before any investigation. This article sets out what the regulation does, where a flooring product touches labour you cannot see, and a document list to send to any flooring supplier. It is general guidance, not legal advice.
What the regulation does, and what it does not
Regulation (EU) 2024/3015 prohibits economic operators from placing or making available on the EU market, or exporting from it, products made with forced labour (Article 1). It applies from 14 December 2027 (Article 39). Three features shape what an importer needs to prepare:
- It works through investigations. The Commission is the lead authority where the suspected forced labour is outside the EU. A national authority leads where it is inside a Member State. The guidelines state that the authority carries the burden of showing credible evidence that forced labour was used to make the products and that the operators placed them on the EU market or exported them.
- It targets products, not whole businesses. According to the guidelines, an investigation concerns products alleged to be made with forced labour, which can be parts, components, whole products or products from a specific factory, not the entire business of an operator.
- It adds no new due diligence duty of its own. Article 1(3) states that the regulation does not create additional due diligence obligations beyond those already in EU or national law. The guidelines add that information an operator supplies does not guarantee that a product escapes a ban decision.
So the practical question for an importer is not “which certificate do I need” but “what could I show an authority about how this product was made, and who in my supply chain can supply it”. Your compliance advisor should confirm how this fits with the other EU laws that apply to you. For the full EU date picture for flooring in 2027, see our compliance calendar.
Where a flooring product touches labour you cannot see
An engineered floor is several materials made in several steps. Each step has people behind it, and not all of them work in the factory that ships the container.
| Point in the product | Why it matters for a labour question |
|---|---|
| Oak wear layer (sawn, sliced or rotary-peeled) | The timber or veneer comes from a mill and a forest owner before it reaches the flooring factory. See how the wear layer is cut. |
| Plywood core and backing layer | Core and backing may come from a different mill, species and place than the oak. See the plywood core questions. |
| Adhesives and finishing materials | Bought from suppliers whose own supply chains the factory may know little about. |
| The factory floor | Direct employees, agency or recruited workers, overtime, housing and pay. |
| Subcontracted steps | Packing, sanding, repair or re-sorting done at another site. |
| Transport and warehousing | Cartons, pallets and loading before the container. |
The guidelines say that scoping should reflect “geographical area, sector, product or company” and be proportionate to company size and available information. They point SMEs and other companies with limited resources to the EU database of forced labour risks for this first scoping step. Use it as a starting point, not as a verdict on any supplier.
The ILO indicators, as questions
The guidelines refer to the ILO’s indicators of forced labour. Among the common circumstances they list are forced recruitment, deception, exploitation of debt, withholding of wages, retention of cash, assets or identity documents, restrictions on workers’ movements, onerous working hours, and degrading living conditions. Each can be turned into a plain question a supplier can answer in writing:
- Do workers pay any recruitment fee, directly or through an agency, and who covers it?
- Does the factory or any labour agent hold workers’ identity documents, savings or wages?
- Are wages paid in full, on time and to the worker’s own account?
- Can workers leave the site and end employment with normal notice?
- Is overtime voluntary, recorded and paid?
- If the factory provides housing, who inspects it?
A factory does not need to answer “perfectly” for the question to be useful. The answer shows whether the company has thought about the topic and keeps records.
Documents an importer can request
The Commission’s guidelines (sections 4.7.1 and 4.7.3) give examples of the information an authority may ask a company for. The same categories make a sensible request list for a flooring supplier. Ask for what exists, and treat a reasoned “we do not have this” as an answer to record.
| Category | Examples to request |
|---|---|
| Policy and governance | A written policy against forced labour, a code of conduct, who in management owns the topic |
| Supplier controls | Supplier code of conduct, contract clauses on forced labour, supplier onboarding and monitoring steps |
| Supply chain map | A list of suppliers and subcontractors for each key step (oak, core, backing, adhesive, finish, packing), with names, addresses and registration numbers |
| Material traceability | A bill of materials, and records that link a finished lot to the incoming material batches it was made from |
| Transaction records | Purchase orders, invoices, packing lists, shipping documents for the lot |
| Production consistency | Production orders and a check that input volumes match output volumes for the product |
| Workforce records | Sample employment contracts, payroll summary, working-hours records, recruitment agency list (with personal data removed as needed) |
| Grievance and remediation | A grievance channel for workers, and records of corrective action when a problem was found |
| Third-party reports | Audit reports, if the factory has them, with the date, scope and auditor stated |
| Training | Training materials for managers and staff on the topic |
Some of this is the same data the EUDR needs for origin. A factory that can link every lot to its raw-material batches answers both. The EUDR article covers the origin side.
A request that works in practice
- Send the list with the request for quotation, not after the order. It sets the expectation early and shows how the supplier replies when asked.
- Ask in writing and ask for dates. A policy with no date and no owner tells you little.
- Ask for the subcontractor list for each step. The guidelines list names and addresses of manufacturers and suppliers for key production steps among the examples, and unknown subcontracting is where gaps appear.
- Compare replies between suppliers, not against a perfect standard. A short, specific, dated reply is better than a long general one.
- Put the duty to inform in the contract. Require notice of changes in raw-material supplier, subcontractor or recruitment agency, and agree what happens to a shipment if a credible allegation arises.
- Keep the file. The guidelines follow a cycle: put the topic into policy, assess risks, prevent and mitigate, monitor, communicate, and cooperate in remediation. A dated file of requests and replies shows that cycle at work.
Self-declarations are evidence of a position, not proof of conditions. Where risk looks higher, the guidelines name document review, supplier self-assessment, on-site inspection, worker interviews and stakeholder engagement as forms of deeper assessment. A visit is part of that toolbox; see how to vet a flooring factory and pre-shipment inspection.
United States and other markets
The US Customs and Border Protection page on forced labor enforcement cites 19 U.S.C. 1307 as the legal basis and describes withhold release orders, findings and importer submissions. The page we opened does not mention wood or timber, and it does not set a flooring-specific document list. If you import into the US, ask your customs broker or counsel how those procedures apply to your supply chain.
Timeline for an importer
- Now to mid-2027. Send the request list to current suppliers, record replies, fix gaps with the largest suppliers first.
- Second half of 2027. Add contract clauses to new purchase orders. Read the Commission guidelines in full, in particular sections 4.7 and 6.4.
- 14 December 2027. The ban applies to products placed on the EU market from this date.
Sources
- Regulation (EU) 2024/3015, Articles 1, 11 and 39 (Official Journal text via the Publications Office; the EUR-Lex page did not open).
- European Commission, Guidelines on the application of Regulation (EU) 2024/3015, Commission Notice C/2026/4637, Official Journal of 3 September 2026: sections 3.4, 4.1, 4.2, 4.7 and 6.4.
- European Commission, Forced Labour Regulation page, opened 25 October 2026.
- US Customs and Border Protection, Forced Labor, last modified 29 September 2026.
- International Labour Organization, indicators of forced labour, as referenced in the Commission guidelines.
Working with Vu Uy Wood
Vu Uy Wood manufactures solid and engineered French White Oak flooring to specification in Song Than 3 Industrial Park, Ho Chi Minh City, and has done so since 2006. If you want to send a supplier questionnaire together with your request for quotation, attach it through the contact page, and we will respond within 24 business hours.